WORK ZONES (CLOSED): 26 to report. Hide

Road Closed due to work zoneState Route MO 111 N North - ATCHISON COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .009 MILE(S) AFTER RP MO111 TO IS29S S.
Scheduled from 20-MAY-2022 to 29-JUL-2022.
Road Closed due to work zoneState Route MO 111 S South - ATCHISON COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .012 MILE(S) AFTER RP IS29N TO MO111 E.
Scheduled from 20-MAY-2022 to 29-JUL-2022.
Road Closed due to work zoneState Route RT E E East - CARROLL COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .487 MILE(S) AFTER CO RTE TO RTD S.
Scheduled from 04-MAY-2022 to 08-AUG-2022.
News Releases - https://www.modot.org/node/25717
Road Closed due to work zoneState Route RT E W West - CARROLL COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .089 MILE(S) AFTER RT PP S.
Scheduled from 04-MAY-2022 to 08-AUG-2022.
News Releases - https://www.modot.org/node/25717
Road Closed due to work zoneState Route RT V N North - CARROLL COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins CRD 296 E.
Scheduled from 23-MAY-2022 to 28-SEP-2022.
Road Closed due to work zoneState Route RT V S South - CARROLL COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .188 MILE(S) BEFORE CRD 296 E.
Scheduled from 23-MAY-2022 to 28-SEP-2022.
Road Closed due to work zoneState Route RT Z N North - CARROLL COUNTY - Road Closed
PAVEMENT REPAIR
Road closure begins .117 MILE(S) AFTER CRD 154 E.
Scheduled from 22-JUN-2022 to 10-AUG-2022.
Road Closed due to work zoneState Route RT Z S South - CARROLL COUNTY - Road Closed
PAVEMENT REPAIR
Road closure begins .043 MILE(S) AFTER RT C E.
Scheduled from 22-JUN-2022 to 10-AUG-2022.
Road Closed due to work zoneUS US 69 N North - CLINTON COUNTY - Road Closed
INTERSECTION IMPROVEMENTS
Road closure begins .005 MILE(S) AFTER RT V E.
Scheduled from 12-APR-2022 to 03-AUG-2022.
Road Closed due to work zoneUS US 69 N North - CLINTON COUNTY - Road Closed
INTERSECTION IMPROVEMENTS
Road closure begins .058 MILE(S) AFTER MO 116 E.
Scheduled from 19-MAY-2022 to 03-AUG-2022.
Road Closed due to work zoneUS US 69 S South - CLINTON COUNTY - Road Closed
INTERSECTION IMPROVEMENTS
Road closure begins .001 MILE(S) AFTER MO 116 E.
Scheduled from 12-APR-2022 to 03-AUG-2022.
Road Closed due to work zoneUS US 69 S South - CLINTON COUNTY - Road Closed
INTERSECTION IMPROVEMENTS
Road closure begins .033 MILE(S) AFTER RT H E.
Scheduled from 19-MAY-2022 to 03-AUG-2022.
Road Closed due to work zoneState Route RT B N North - GENTRY COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .012 MILE(S) AFTER CRD 257 ST E.
Scheduled from 02-MAY-2022 to 22-JUL-2022.
News Releases - https://www.modot.org/node/25630
Road Closed due to work zoneState Route RT B S South - GENTRY COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .015 MILE(S) AFTER CRD 247 ST E.
Scheduled from 02-MAY-2022 to 22-JUL-2022.
News Releases - https://www.modot.org/node/25630
Road Closed due to work zoneState Route RT A E East - HARRISON COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .001 MILE(S) AFTER RP IS35S TO RTA S.
Scheduled from 16-MAY-2022 to 20-SEP-2022.
Road Closed due to work zoneState Route RT A W West - HARRISON COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .002 MILE(S) AFTER RP RTA TO IS35N N.
Scheduled from 16-MAY-2022 to 20-SEP-2022.
Road Closed due to work zoneState Route MO 111 N North - HOLT COUNTY - Road Closed
INTERSECTION IMPROVEMENTS
Road closure begins .004 MILE(S) AFTER US 159 S.
Scheduled from 31-MAY-2022 to 08-JUL-2022.
Road Closed due to work zoneState Route MO 111 S South - HOLT COUNTY - Road Closed
INTERSECTION IMPROVEMENTS
Road closure begins .142 MILE(S) BEFORE RR ST JOSEPH SUB S.
Scheduled from 31-MAY-2022 to 08-JUL-2022.
Road Closed due to work zoneUS US 59 N North - HOLT COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .004 MILE(S) AFTER RP IS29S TO US59 S.
Scheduled from 06-APR-2022 to 18-SEP-2022.
Road Closed due to work zoneUS US 59 N North - HOLT COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .002 MILE(S) AFTER OR 29 S.
Scheduled from 06-APR-2022 to 29-JUL-2022.
Road Closed due to work zoneUS US 59 S South - HOLT COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .006 MILE(S) AFTER RP IS29N TO US59 N.
Scheduled from 06-APR-2022 to 29-JUL-2022.
Road Closed due to work zoneUS US 59 S South - HOLT COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .005 MILE(S) AFTER CRD DAISY RD S.
Scheduled from 06-APR-2022 to 18-SEP-2022.
Road Closed due to work zoneState Route RT D E East - MERCER COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .018 MILE(S) AFTER CRD IBERIA ST E.
Scheduled from 20-JUN-2022 to 14-AUG-2022.
Road Closed due to work zoneState Route RT D W West - MERCER COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .145 MILE(S) AFTER CRD ICARUS PL E.
Scheduled from 20-JUN-2022 to 14-AUG-2022.
Road Closed due to work zoneUS US 136 E East - NODAWAY COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .017 MILE(S) AFTER CRD LIBERTY RD S.
Scheduled from 11-MAY-2022 to 30-SEP-2022.
Road Closed due to work zoneUS US 136 W West - NODAWAY COUNTY - Road Closed
BRIDGE RECONSTRUCTION
Road closure begins .027 MILE(S) AFTER RT E S.
Scheduled from 11-MAY-2022 to 30-SEP-2022.

Back to Top

WORK ZONES (EXPECT DELAYS, POSSIBLE DELAYS): 28 to report. Hide

Expect delays due to work zoneState Route RT M N North - ANDREW COUNTY - Expect Delays
RESURFACING PAVEMENT
Scheduled from 01-JUL-2022 to 31-JUL-2022.
Road work begins US 169 S.
Work will be done around the clock, on weekdays and Saturdays.
Expect delays due to work zoneState Route RT M S South - ANDREW COUNTY - Expect Delays
RESURFACING PAVEMENT
Scheduled from 01-JUL-2022 to 31-JUL-2022.
Road work begins MO 48 E.
Work will be done around the clock, on weekdays and Saturdays.
Expect delays due to work zoneInterstate IS 29 N North - ATCHISON COUNTY - Expect Delays
Project Name - REHABILITATION OF THE SB NISHNABOTNA BRIDGe
BRIDGE RECONSTRUCTION
Scheduled from 01-MAR-2022 to 31-AUG-2022.
Road work begins .011 MILE(S) AFTER WS IS29N WATSON N.
Work will be done around the clock, 7 days a week.
Expect delays due to work zoneInterstate IS 29 S South - ATCHISON COUNTY - Expect Delays
Project Name - REHABILITATION OF THE SB NISHNABOTNA BRIDGe
BRIDGE RECONSTRUCTION
Scheduled from 01-MAR-2022 to 31-AUG-2022.
Road work begins 1.938 MILE(S) BEFORE CRD C AVE S.
Work will be done around the clock, 7 days a week.
Expect delays due to work zoneUS US 36 E East - BUCHANAN COUNTY - Expect Delays
BRIDGE RECONSTRUCTION
Scheduled from 31-JAN-2022 to 01-DEC-2022.
Road work begins .142 MILE(S) BEFORE RP US36E TO MO759S S.
Work will be done around the clock, 7 days a week.
Expect delays due to work zoneUS US 36 W West - BUCHANAN COUNTY - Expect Delays
BRIDGE RECONSTRUCTION
Scheduled from 31-JAN-2022 to 01-DEC-2022.
Road work begins .006 MILE(S) BEFORE RP US36W TO IS229S S.
Work will be done around the clock, 7 days a week.
Expect delays due to work zoneInterstate IS 35 N North - CLINTON COUNTY - Expect Delays
RESURFACING PAVEMENT
Scheduled from 09-MAY-2022 to 16-AUG-2022.
Road work begins .062 MILE(S) BEFORE RT BB S.
Work will be done around the clock, on weekdays and Saturdays.
Expect delays due to work zoneState Route MO 116 E East - CLINTON COUNTY - Expect Delays
INTERSECTION IMPROVEMENTS
Scheduled from 19-MAY-2022 to 03-AUG-2022.
Road work begins .061 MILE(S) AFTER CRD SE FAGIN LN S.
Work will be done around the clock, 7 days a week.
Expect delays due to work zoneState Route MO 116 W West - CLINTON COUNTY - Expect Delays
INTERSECTION IMPROVEMENTS
Scheduled from 19-MAY-2022 to 03-AUG-2022.
Road work begins .219 MILE(S) AFTER CRD NE 256TH ST E.
Work will be done around the clock, 7 days a week.
Possible delays due to work zoneState Route RT PP E East - CLINTON COUNTY - Delays Possible
PERMIT OR UTILITY WORK
Scheduled from 16-JUN-2022 to 22-JUL-2022.
Road work begins .005 MILE(S) AFTER CRD CAMERON RD S.
Work will be done around the clock, on weekdays only.
Possible delays due to work zoneUS US 69 S South - CLINTON COUNTY - Delays Possible
PERMIT OR UTILITY WORK
Scheduled from 16-JUN-2022 to 22-JUL-2022.
Road work begins CRD SE 210TH ST E.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneInterstate IS 35 S South - DAVIESS COUNTY - Expect Delays
RESURFACING PAVEMENT
Scheduled from 09-MAY-2022 to 16-AUG-2022.
Road work begins .434 MILE(S) BEFORE RP IS35S TO US69 S.
Work will be done around the clock, on weekdays and Saturdays.
Expect delays due to work zoneUS US 36 E East - DEKALB COUNTY - Expect Delays
PAVEMENT REPAIR
Scheduled from 07-MAR-2022 to 16-JUL-2022.
Road work begins .454 MILE(S) AFTER CST BOB F GRIFFIN RD S.
Work will be done around the clock, on weekdays and Saturdays.
Expect delays due to work zoneUS US 36 W West - DEKALB COUNTY - Expect Delays
PAVEMENT REPAIR
Scheduled from 21-MAR-2022 to 16-JUL-2022.
Road work begins .08 MILE(S) BEFORE CRD TAYLOR RD S.
Work will be done around the clock, on weekdays and Saturdays.
Expect delays due to work zoneInterstate IS 35 N North - HARRISON COUNTY - Expect Delays
Project Name - BRIDGE REHABILITATION - POLE CAT CREEK
BRIDGE RECONSTRUCTION
Scheduled from 15-MAR-2022 to 30-SEP-2022.
Road work begins .988 MILE(S) AFTER RP MO13 TO IS35N N.
Work will be done around the clock, 7 days a week.
Project Web Page - HTTPS://WWW.MODOT.ORG/NODE/25133
Expect delays due to work zoneInterstate IS 35 S South - HARRISON COUNTY - Expect Delays
Project Name - BRIDGE REHABILITATION - POLE CAT CREEK
BRIDGE RECONSTRUCTION
Scheduled from 15-MAR-2022 to 30-SEP-2022.
Road work begins 1.552 MILE(S) BEFORE RP IS35S TO MO13 S.
Work will be done around the clock, 7 days a week.
Project Web Page - HTTPS://WWW.MODOT.ORG/NODE/25133
Possible delays due to work zoneInterstate IS 35 N North - HARRISON COUNTY - Delays Possible
BRIDGE RECONSTRUCTION
Scheduled from 16-MAY-2022 to 20-SEP-2022.
Road work begins .796 MILE(S) BEFORE RP IS35N TO RTA N.
Work will be done around the clock, 7 days a week.
Possible delays due to work zoneInterstate IS 35 S South - HARRISON COUNTY - Delays Possible
BRIDGE RECONSTRUCTION
Scheduled from 16-MAY-2022 to 20-SEP-2022.
Road work begins .792 MILE(S) BEFORE RP IS35S TO RTA S.
Work will be done around the clock, 7 days a week.
Expect delays due to work zoneInterstate IS 29 N North - HOLT COUNTY - Expect Delays
BRIDGE RECONSTRUCTION
Scheduled from 24-MAY-2022 to 29-JUL-2022.
Road work begins .072 MILE(S) AFTER RP IS29N TO US59 N.
Work will be done around the clock, 7 days a week.
Expect delays due to work zoneInterstate IS 29 S South - HOLT COUNTY - Expect Delays
BRIDGE RECONSTRUCTION
Scheduled from 06-APR-2022 to 29-JUL-2022.
Road work begins .042 MILE(S) AFTER RP IS29S TO US59 S.
Work will be done around the clock, 7 days a week.
Project Web Page - https://www.modot.org/holt-county-i-29-bridge-deck-replacement-over-us-route-59
Expect delays due to work zoneUS US 159 N North - HOLT COUNTY - Expect Delays
RESURFACING PAVEMENT
Scheduled from 17-MAY-2022 to 06-DEC-2022.
Road work begins .52 MILE(S) BEFORE CRD OLD 159 E.
Work will be done around the clock, 7 days a week.
Expect delays due to work zoneUS US 159 N North - HOLT COUNTY - Expect Delays
BRIDGE MAINTENANCE
Scheduled from 23-MAY-2022 to 22-JUL-2022.
Road work begins .024 MILE(S) AFTER CRD DIAMOND LN S.
Work will be done around the clock, 7 days a week.
Expect delays due to work zoneUS US 159 S South - HOLT COUNTY - Expect Delays
BRIDGE MAINTENANCE
Scheduled from 23-MAY-2022 to 22-JUL-2022.
Road work begins .035 MILE(S) AFTER CRD EMBER RD S.
Work will be done around the clock, 7 days a week.
Expect delays due to work zoneUS US 159 S South - HOLT COUNTY - Expect Delays
RESURFACING PAVEMENT
Scheduled from 17-MAY-2022 to 06-DEC-2022.
Road work begins .032 MILE(S) AFTER RT P S.
Work will be done around the clock, 7 days a week.
Possible delays due to work zoneUS US 36 W West - LINN COUNTY - Delays Possible
PAVEMENT REPAIR
Scheduled from 13-JUN-2022 to 31-AUG-2022.
Road work begins .527 MILE(S) BEFORE CO US36W TO US36E S.
Work will be done around the clock, on weekdays and Saturdays.
Possible delays due to work zoneUS US 36 E East - LIVINGSTON COUNTY - Delays Possible
PAVEMENT REPAIR
Scheduled from 13-JUN-2022 to 31-AUG-2022.
Road work begins .029 MILE(S) AFTER CST NETTLETON ST E.
Work will be done around the clock, on weekdays and Saturdays.
Expect delays due to work zoneUS US 136 E East - NODAWAY COUNTY - Expect Delays
BRIDGE RECONSTRUCTION
Scheduled from 02-MAY-2022 to 02-SEP-2022.
Road work begins .003 MILE(S) AFTER CRD LIBERTY RD S.
Work will be done around the clock, 7 days a week.
Expect delays due to work zoneUS US 136 W West - NODAWAY COUNTY - Expect Delays
BRIDGE RECONSTRUCTION
Scheduled from 02-MAY-2022 to 02-SEP-2022.
Road work begins .003 MILE(S) AFTER RT MM S.
Work will be done around the clock, 7 days a week.

Back to Top

FUTURE WORK ZONES: 37 to report. Hide

Possible delays due to work zoneState Route MO 48 E East - ANDREW COUNTY - Delays Possible
PATCHING DRIVE SURFACE
Scheduled from 07-JUL-2022 to 07-JUL-2022.
Road work begins .018 MILE(S) AFTER CRD 149 E.
Work will be done around the clock, on weekdays only.
Possible delays due to work zoneState Route RT U S South - ANDREW COUNTY - Delays Possible
PATCHING DRIVE SURFACE
Scheduled from 05-JUL-2022 to 05-JUL-2022.
Road work begins .111 MILE(S) BEFORE CRD 6 E.
Work will be done around the clock, on weekdays only.
Possible delays due to work zoneState Route RT Y N North - ANDREW COUNTY - Delays Possible
PATCHING DRIVE SURFACE
Scheduled from 06-JUL-2022 to 06-JUL-2022.
Road work begins .431 MILE(S) AFTER US 71 S.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT M N North - ATCHISON COUNTY - CLOSED
CHIP SEAL OVERLAY
Scheduled from 08-JUL-2022 to 08-JUL-2022.
Road work begins .027 MILE(S) BEFORE RT C E.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT N N North - ATCHISON COUNTY - Expect Delays
CHIP SEAL OVERLAY
Scheduled from 05-JUL-2022 to 06-JUL-2022.
Road work begins CRD ATCHISON HOLT RD E.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT P E East - BUCHANAN COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 05-JUL-2022 to 07-JUL-2022.
Road work begins RT UU S.
Work will be done around the clock, on weekdays only.
Possible delays due to work zoneLoop LP 29 N North - BUCHANAN COUNTY - Delays Possible
PERMIT OR UTILITY WORK
Scheduled from 05-JUL-2022 to 26-AUG-2022.
Road work begins CST 31ST ST S.
Work will be done around the clock, 7 days a week.
Possible delays due to work zoneLoop LP 29 S South - BUCHANAN COUNTY - Delays Possible
PERMIT OR UTILITY WORK
Scheduled from 05-JUL-2022 to 26-AUG-2022.
Road work begins CST 29TH ST S.
Work will be done around the clock, 7 days a week.
Possible delays due to work zoneState Route MO 371 S South - BUCHANAN COUNTY - Delays Possible
ROADSIDE WORK
Scheduled from 05-JUL-2022 to 05-JUL-2022.
Road work begins .006 MILE(S) AFTER CRD SEYMOUR SE E.
Work will be done around the clock, on weekdays only.
Possible delays due to work zoneState Route MO 752 E East - BUCHANAN COUNTY - Delays Possible
PERMIT OR UTILITY WORK
Scheduled from 05-JUL-2022 to 17-JUL-2022.
Road work begins .028 MILE(S) BEFORE CST 3RD ST S.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT YY S South - CARROLL COUNTY - CLOSED
PATCHING DRIVE SURFACE
Scheduled from 05-JUL-2022 to 08-JUL-2022.
Road work begins RT J E.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT P N North - CHARITON COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 07-JUL-2022 to 07-JUL-2022.
Road work begins .001 MILE(S) AFTER CRD MENEFEE RD E.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT P N North - CHARITON COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 07-JUL-2022 to 07-JUL-2022.
Road work begins .006 MILE(S) BEFORE CRD CROPP RD S.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT P S South - CHARITON COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 07-JUL-2022 to 07-JUL-2022.
Road work begins CRD PUZZLE LN S.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT H E East - CLINTON COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 06-JUL-2022 to 06-JUL-2022.
Road work begins .005 MILE(S) BEFORE CRD NE SILVUS RD S.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route MO 33 S South - CLINTON COUNTY - Expect Delays
ROADSIDE WORK
Scheduled from 05-JUL-2022 to 08-JUL-2022.
Road work begins .002 MILE(S) BEFORE CRD SE 209TH ST E.
Work will be done around the clock, on weekdays only.
Possible delays due to work zoneState Route MO 6 W West - DAVIESS COUNTY - Delays Possible
SHOULDER WORK
Scheduled from 07-JUL-2022 to 07-JUL-2022.
Road work begins .035 MILE(S) BEFORE CST SECOND ST E.
Work will be done around the clock, on weekdays only.
Possible delays due to work zoneState Route RT K N North - DAVIESS COUNTY - Delays Possible
PATCHING DRIVE SURFACE
Scheduled from 05-JUL-2022 to 06-JUL-2022.
Road work begins MO 6 E.
Work will be done around the clock, on weekdays only.
Possible delays due to work zoneState Route RT P W West - DAVIESS COUNTY - Delays Possible
PATCHING DRIVE SURFACE
Scheduled from 06-JUL-2022 to 07-JUL-2022.
Road work begins .248 MILE(S) BEFORE CRD 65 S.
Work will be done around the clock, on weekdays only.
Possible delays due to work zoneState Route RT M W West - GENTRY COUNTY - Delays Possible
PATCHING DRIVE SURFACE
Scheduled from 05-JUL-2022 to 08-JUL-2022.
Road work begins US 169 S.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT B W West - GRUNDY COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 06-JUL-2022 to 06-JUL-2022.
Road work begins RT Y S.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT C E East - GRUNDY COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 05-JUL-2022 to 05-JUL-2022.
Road work begins .002 MILE(S) AFTER CRD 95TH ST E.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT NN S South - GRUNDY COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 07-JUL-2022 to 07-JUL-2022.
Road work begins .001 MILE(S) BEFORE CRD NE GEODE LN E.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT NN S South - GRUNDY COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 08-JUL-2022 to 08-JUL-2022.
Road work begins .004 MILE(S) BEFORE RT O E.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT N N North - HOLT COUNTY - Expect Delays
CHIP SEAL OVERLAY
Scheduled from 05-JUL-2022 to 05-JUL-2022.
Road work begins US 59 S.
Work will be done around the clock, on weekdays only.
Possible delays due to work zoneState Route RT C E East - HOLT COUNTY - Delays Possible
CULVERT REPLACEMENT
Scheduled from 07-JUL-2022 to 08-JUL-2022.
Road work begins US 59 S.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT V N North - LINN COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 06-JUL-2022 to 06-JUL-2022.
Road work begins CRD INDIGO RD E.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT V N North - LINN COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 07-JUL-2022 to 07-JUL-2022.
Road work begins .002 MILE(S) BEFORE CRD INGEL RD E.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT KK N North - NODAWAY COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 05-JUL-2022 to 05-JUL-2022.
Road work begins .007 MILE(S) BEFORE CRD 160 ST E.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT YY S South - NODAWAY COUNTY - CLOSED
CHIP SEAL OVERLAY
Scheduled from 07-JUL-2022 to 07-JUL-2022.
Road work begins .003 MILE(S) AFTER RT C E.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneUS US 71 N North - NODAWAY COUNTY - Expect Delays
PATCHING DRIVE SURFACE
Scheduled from 07-JUL-2022 to 07-JUL-2022.
Road work begins CRD 410 ST E.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT BB S South - PUTNAM COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 06-JUL-2022 to 06-JUL-2022.
Road work begins .016 MILE(S) AFTER RT EE S.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT EE S South - PUTNAM COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 05-JUL-2022 to 08-JUL-2022.
Road work begins US 136 E.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT BB S South - SULLIVAN COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 05-JUL-2022 to 05-JUL-2022.
Road work begins .009 MILE(S) BEFORE CRD JOINER RD E.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT M E East - SULLIVAN COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 07-JUL-2022 to 07-JUL-2022.
Road work begins .012 MILE(S) AFTER CRD FAIR DR S.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT M E East - SULLIVAN COUNTY - CLOSED
CULVERT REPLACEMENT
Scheduled from 08-JUL-2022 to 08-JUL-2022.
Road work begins MO 5 S.
Work will be done around the clock, on weekdays only.
Expect delays due to work zoneState Route RT M E East - WORTH COUNTY - CLOSED
ROADSIDE WORK
Scheduled from 06-JUL-2022 to 06-JUL-2022.
Road work begins .016 MILE(S) AFTER RT C S.
Work will be done around the clock, on weekdays only.

Back to Top

INCIDENTS: 6 to report. Show

Back to Top

WINTER ROAD CONDITIONS: 117 to report. Show

Back to Top

Winter Road Conditions Note: The odd numbered routes report generally from north to south and the even numbered routes report generally from west to east. The lettered routes are typically specific to a particular county and likely are not continuous from county to county or through the state.

END OF REPORT