CST FRONT ST S South
-
BARRY COUNTY
- Expect Delays
SIDEWALK/ADA IMPROVEMENTS
Scheduled from 18-APR-2025 to 30-MAY-2025.
Road work begins
.041 MILE(S) AFTER CST LOCUST ST E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
06:00 PM.
CST WASHBURN ST S South
-
BARRY COUNTY
- Expect Delays
SIDEWALK/ADA IMPROVEMENTS
Scheduled from 18-APR-2025 to 30-MAY-2025.
Road work begins
CST LOCUST ST E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
06:00 PM.
State Route MO 39 N North
-
BARRY COUNTY
- Expect Delays
LIGHTING/SIGNAL/SIGN WORK
Scheduled from 11-MAY-2025 to 31-AUG-2025.
Road work begins
.167 MILE(S) BEFORE MO 76 E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
08:00 PM.
State Route MO 39 S South
-
BARRY COUNTY
- Expect Delays
LIGHTING/SIGNAL/SIGN WORK
Scheduled from 11-MAY-2025 to 31-AUG-2025.
Road work begins
.108 MILE(S) BEFORE MO 248 E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
08:00 PM.
State Route MO 86 E East
-
BARRY COUNTY
- Expect Delays
SIDEWALK/ADA IMPROVEMENTS
Scheduled from 18-APR-2025 to 30-MAY-2025.
Road work begins
.009 MILE(S) BEFORE RT CC S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
06:00 PM.
State Route MO 86 W West
-
BARRY COUNTY
- Expect Delays
SIDEWALK/ADA IMPROVEMENTS
Scheduled from 18-APR-2025 to 30-MAY-2025.
Road work begins
CST ENTERPRISE ST S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
06:00 PM.
State Route RT A N North
-
BENTON COUNTY
- Expect Delays
RESURFACING PAVEMENT
Scheduled from 08-MAY-2025 to 09-JUN-2025.
Road work begins
MO 52 E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
06:00 PM.
State Route RT A S South
-
BENTON COUNTY
- Expect Delays
RESURFACING PAVEMENT
Scheduled from 08-MAY-2025 to 09-JUN-2025.
Road work begins
CRD WHITEMAN RD E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
06:00 PM.
State Route RT W N North
-
BENTON COUNTY
- Expect Delays
MILLING/RESURFACING WORK
Scheduled from 12-MAY-2025 to 09-JUN-2025.
Road work begins
RT H E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
06:00 PM.
State Route RT W S South
-
BENTON COUNTY
- Expect Delays
MILLING/RESURFACING WORK
Scheduled from 12-MAY-2025 to 09-JUN-2025.
Road work begins
MO 52 E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
06:00 PM.
State Route RT DD N North
-
BENTON COUNTY
- Delays Possible
RESURFACING PAVEMENT
Scheduled from 12-MAY-2025 to 09-JUN-2025.
Road work begins
MO 7 S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
06:00 PM.
State Route RT DD S South
-
BENTON COUNTY
- Delays Possible
RESURFACING PAVEMENT
Scheduled from 12-MAY-2025 to 09-JUN-2025.
Road work begins
CRD MAIDEN RD E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
06:00 PM.
State Route RT EE E East
-
CEDAR COUNTY
- No Expected Delays
CORE DRILLING
Scheduled from 19-MAY-2025 to 23-MAY-2025.
Road work begins
.738 MILE(S) AFTER CRD SW 1501 S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
06:00 PM.
State Route RT EE W West
-
CEDAR COUNTY
- No Expected Delays
CORE DRILLING
Scheduled from 19-MAY-2025 to 23-MAY-2025.
Road work begins
.339 MILE(S) AFTER CRD 50 E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
06:00 PM.
US US 65 N North
-
CHRISTIAN COUNTY
- Expect Delays
NEW PAVEMENT CONSTRUCTION
Scheduled from 13-NOV-2023 to 01-NOV-2025.
Road work begins
.023 MILE(S) BEFORE RT F E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
04:00 PM.
US US 65 S South
-
CHRISTIAN COUNTY
- Expect Delays
NEW PAVEMENT CONSTRUCTION
Scheduled from 13-NOV-2023 to 01-NOV-2025.
Road work begins
.011 MILE(S) BEFORE RT CC E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
04:00 PM.
US US 160 E East
-
DADE COUNTY
- Expect Delays
CULVERT REPLACEMENT
Scheduled from 14-APR-2025 to 14-JUL-2025.
Road work begins
.246 MILE(S) AFTER CST FOURTH ST E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
07:00 PM.
US US 160 W West
-
DADE COUNTY
- Expect Delays
CULVERT REPLACEMENT
Scheduled from 14-APR-2025 to 14-JUL-2025.
Road work begins
.001 MILE(S) AFTER MO 39 S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
07:00 PM.
State Route RT DD E East
-
DALLAS COUNTY
- Delays Possible
MILLING/RESURFACING WORK
Scheduled from 19-MAY-2025 to 02-JUN-2025.
Road work begins
MO 73 S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
07:00 PM.
State Route RT DD W West
-
DALLAS COUNTY
- Delays Possible
MILLING/RESURFACING WORK
Scheduled from 19-MAY-2025 to 02-JUN-2025.
Road work begins
CRD HACKBERRY RD E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
07:00 PM.
CST CHESTNUT EXPY E East
-
GREENE COUNTY
- Expect Delays
SIDEWALK/ADA IMPROVEMENTS
Scheduled from 16-DEC-2024 to 30-JUN-2026.
Road work begins
.003 MILE(S) BEFORE LP 44 E.
Work will be done
on weekdays only.
CST CHESTNUT EXPY W West
-
GREENE COUNTY
- Expect Delays
SIDEWALK/ADA IMPROVEMENTS
Scheduled from 16-DEC-2024 to 30-JUN-2026.
Road work begins
.001 MILE(S) AFTER OR 65 S.
Work will be done
on weekdays only.
CST GLENSTONE AVE N North
-
GREENE COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 07-APR-2025 to 31-MAY-2025.
Road work begins
.015 MILE(S) BEFORE US 60 E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
08:00 PM
and
06:00 AM.
CST GLENSTONE AVE N North
-
GREENE COUNTY
- Expect Delays
ROADSIDE WORK
Scheduled from 14-MAY-2025 to 21-MAY-2025.
Road work begins
.003 MILE(S) BEFORE CST DIVISION ST E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
06:00 PM.
CST GLENSTONE AVE S South
-
GREENE COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 07-APR-2025 to 31-MAY-2025.
Road work begins
.019 MILE(S) BEFORE US 60 W.
Work will be done
on weekdays only.
Work will be conducted between the hours of
08:00 PM
and
06:00 AM.
CST REPUBLIC ST E East
-
GREENE COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 13-MAY-2025 to 31-MAY-2025.
Road work begins
.042 MILE(S) BEFORE US 60 W.
Work will be done
on weekdays only.
Work will be conducted between the hours of
08:00 PM
and
06:00 AM.
CST REPUBLIC ST W West
-
GREENE COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 13-MAY-2025 to 31-MAY-2025.
Road work begins
.012 MILE(S) BEFORE CST MONASTERY ST E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
08:00 PM
and
06:00 AM.
Interstate IS 44 E East
-
GREENE COUNTY
- Expect Delays
NEW PAVEMENT CONSTRUCTION
Scheduled from 10-MAR-2025 to 21-MAY-2027.
Road work begins
.054 MILE(S) AFTER RP IS44E TO MO13S S.
Work will be done
on weekdays and Saturdays.
Work will be conducted between the hours of
08:00 PM
and
06:00 AM.
Interstate IS 44 E East
-
GREENE COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 18-MAY-2025 to 24-MAY-2025.
Road work begins
.089 MILE(S) BEFORE RR FORT SCOTT SUB E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 PM
and
07:00 AM.
Interstate IS 44 W West
-
GREENE COUNTY
- Expect Delays
NEW PAVEMENT CONSTRUCTION
Scheduled from 10-MAR-2025 to 21-MAY-2027.
Road work begins
.002 MILE(S) AFTER US 65 S.
Work will be done
on weekdays and Saturdays.
Work will be conducted between the hours of
08:00 PM
and
06:00 AM.
Interstate IS 44 W West
-
GREENE COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 18-MAY-2025 to 24-MAY-2025.
Road work begins
.277 MILE(S) AFTER RT EE E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 PM
and
07:00 AM.
Interstate IS 44 W West
-
GREENE COUNTY
- Expect Delays
NEW PAVEMENT CONSTRUCTION
Scheduled from 21-APR-2025 to 21-OCT-2025.
Road work begins
.69 MILE(S) AFTER RP MO744 TO IS44W W.
Work will be done
7 days a week.
Loop LP 44 E East
-
GREENE COUNTY
- Expect Delays
SIDEWALK/ADA IMPROVEMENTS
Scheduled from 16-DEC-2024 to 30-JUN-2026.
Road work begins
.009 MILE(S) AFTER OR 44 E.
Work will be done
on weekdays only.
Loop LP 44 W West
-
GREENE COUNTY
- Expect Delays
SIDEWALK/ADA IMPROVEMENTS
Scheduled from 16-DEC-2024 to 30-JUN-2026.
Road work begins
.005 MILE(S) BEFORE BU 65 S.
Work will be done
on weekdays only.
State Route MO 125 N North
-
GREENE COUNTY
- Expect Delays
NEW PAVEMENT CONSTRUCTION
Scheduled from 10-MAR-2025 to 22-MAY-2026.
Road work begins
.09 MILE(S) AFTER CST OLD ORCHARD DR S.
Work will be done
on weekdays only.
State Route MO 125 S South
-
GREENE COUNTY
- Expect Delays
NEW PAVEMENT CONSTRUCTION
Scheduled from 10-MAR-2025 to 22-MAY-2026.
Road work begins
.008 MILE(S) BEFORE OR 44 E.
Work will be done
on weekdays only.
State Route MO 744 E East
-
GREENE COUNTY
- Expect Delays
RESURFACING PAVEMENT
Scheduled from 10-JUN-2024 to 31-JUL-2025.
Road work begins
US 160 W.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
06:00 PM.
State Route MO 744 E East
-
GREENE COUNTY
- Expect Delays
RESURFACING PAVEMENT
Scheduled from 06-MAY-2025 to 27-MAY-2025.
Road work begins
.01 MILE(S) AFTER CST KEARNEY ST E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
08:00 PM
and
06:00 AM.
State Route MO 744 W West
-
GREENE COUNTY
- Expect Delays
RESURFACING PAVEMENT
Scheduled from 10-JUN-2024 to 31-JUL-2025.
Road work begins
.001 MILE(S) AFTER RT OO E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
06:00 PM.
State Route MO 744 W West
-
GREENE COUNTY
- Expect Delays
RESURFACING PAVEMENT
Scheduled from 06-MAY-2025 to 27-MAY-2025.
Road work begins
.005 MILE(S) AFTER US 160 E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
08:00 PM
and
06:00 AM.
State Route RT TT E East
-
GREENE COUNTY
- Expect Delays
RESURFACING PAVEMENT
Scheduled from 19-MAY-2025 to 22-MAY-2025.
Road work begins
.066 MILE(S) AFTER RT PP S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
04:00 PM.
US US 60 E East
-
GREENE COUNTY
- Expect Delays
RESURFACING PAVEMENT
Scheduled from 14-APR-2025 to 20-JUN-2025.
Road work begins
.009 MILE(S) AFTER MO 13 S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
08:00 PM
and
06:00 AM.
US US 60 W West
-
GREENE COUNTY
- Expect Delays
RESURFACING PAVEMENT
Scheduled from 14-APR-2025 to 20-JUN-2025.
Road work begins
.025 MILE(S) AFTER CST NATIONAL AVE N.
Work will be done
on weekdays only.
Work will be conducted between the hours of
08:00 PM
and
06:00 AM.
Interstate IS 44 E East
-
GREENE COUNTY
- Delays Possible
CONCRETE OVERLAY
Scheduled from 18-MAY-2025 to 19-MAY-2025.
Road work begins
1.18 MILE(S) BEFORE RP IS44E TO MO125 E.
Work will be done
on weekdays and Sundays.
Work will be conducted between the hours of
08:30 PM
and
07:00 AM.
State Route MO 13 N North
-
HENRY COUNTY
- Expect Delays
BRIDGE RECONSTRUCTION
Scheduled from 05-AUG-2024 to 01-NOV-2025.
Road work begins
.063 MILE(S) AFTER MO 52 E.
Work will be done
7 days a week.
State Route MO 13 S South
-
HENRY COUNTY
- Expect Delays
BRIDGE RECONSTRUCTION
Scheduled from 05-AUG-2024 to 01-NOV-2025.
Road work begins
.012 MILE(S) BEFORE CRD SW 450TH RD E.
Work will be done
7 days a week.
State Route RT W N North
-
HENRY COUNTY
- Expect Delays
MILLING/RESURFACING WORK
Scheduled from 05-MAY-2025 to 19-MAY-2025.
Road work begins
CRD SE-561 E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
06:00 PM.
State Route RT W S South
-
HENRY COUNTY
- Expect Delays
MILLING/RESURFACING WORK
Scheduled from 05-MAY-2025 to 19-MAY-2025.
Road work begins
MO 7 S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
06:00 PM.
State Route MO 13 N North
-
HENRY COUNTY
- No Expected Delays
CORE DRILLING
Scheduled from 18-MAY-2025 to 23-MAY-2025.
Road work begins
.219 MILE(S) AFTER RT Z E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
06:00 PM.
Interstate IS 49 N North
-
JASPER COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 19-MAY-2025 to 30-MAY-2025.
Road work begins
.335 MILE(S) BEFORE RP IS49N TO RTH E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
07:00 PM.
Interstate IS 49 S South
-
JASPER COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 19-MAY-2025 to 30-MAY-2025.
Road work begins
.162 MILE(S) BEFORE CRD JACKPINE RD E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
07:00 PM.
Interstate IS 49 S South
-
JASPER COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 19-MAY-2025 to 30-MAY-2025.
Road work begins
.013 MILE(S) AFTER MO 571 S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
07:00 PM.
State Route MO 171 N North
-
JASPER COUNTY
- Expect Delays
BRIDGE RECONSTRUCTION
Scheduled from 12-MAY-2025 to 19-MAY-2025.
Road work begins
.019 MILE(S) BEFORE MO 96 W.
Work will be done
7 days a week.
State Route MO 171 S South
-
JASPER COUNTY
- Expect Delays
BRIDGE RECONSTRUCTION
Scheduled from 12-MAY-2025 to 19-MAY-2025.
Road work begins
.006 MILE(S) AFTER RP MO171S TO MO96 E.
Work will be done
7 days a week.
State Route MO 96 W West
-
JASPER COUNTY
- Expect Delays
BRIDGE RECONSTRUCTION
Scheduled from 12-MAY-2025 to 30-AUG-2025.
Road work begins
.002 MILE(S) AFTER MO 171 N.
Work will be done
7 days a week.
Ramp RP MO171S TO MO96W W West
-
JASPER COUNTY
- Expect Delays
BRIDGE RECONSTRUCTION
Scheduled from 12-MAY-2025 to 30-AUG-2025.
Road work begins
MO 171 S.
Work will be done
7 days a week.
Ramp RP MO96 TO MO171N N North
-
JASPER COUNTY
- Expect Delays
BRIDGE RECONSTRUCTION
Scheduled from 12-MAY-2025 to 30-AUG-2025.
Road work begins
MO 96 E.
Work will be done
7 days a week.
Ramp RP MO96 TO MO171S S South
-
JASPER COUNTY
- Expect Delays
BRIDGE RECONSTRUCTION
Scheduled from 12-MAY-2025 to 30-AUG-2025.
Road work begins
MO 96 E.
Work will be done
7 days a week.
Interstate IS 44 E East
-
LAWRENCE COUNTY
- Expect Delays
PAVEMENT REPAIR
Scheduled from 18-MAY-2025 to 31-MAY-2025.
Road work begins
.831 MILE(S) BEFORE CRD 1222 S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 PM
and
07:00 AM.
Interstate IS 44 W West
-
LAWRENCE COUNTY
- Expect Delays
PAVEMENT REPAIR
Scheduled from 18-MAY-2025 to 31-MAY-2025.
Road work begins
.083 MILE(S) BEFORE CRD 1222 S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 PM
and
07:00 AM.
State Route MO 39 S South
-
LAWRENCE COUNTY
- Expect Delays
LIGHTING/SIGNAL/SIGN WORK
Scheduled from 09-MAY-2025 to 20-MAY-2025.
Road work begins
.082 MILE(S) BEFORE RR AURORA SUB E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
08:00 PM.
CRD DAVID DR E East
-
NEWTON COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 10-MAR-2025 to 09-FEB-2026.
Road work begins
.024 MILE(S) BEFORE IS 49 S.
Work will be done
7 days a week.
CRD DAVID DR W West
-
NEWTON COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 10-MAR-2025 to 09-FEB-2026.
Road work begins
.014 MILE(S) AFTER PVT IVEYRIDGE LN S.
Work will be done
7 days a week.
Interstate IS 44 E East
-
NEWTON COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 23-MAR-2025 to 02-JUL-2025.
Road work begins
.02 MILE(S) AFTER MO 43 S.
Work will be done
7 days a week.
Interstate IS 44 E East
-
NEWTON COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 30-MAR-2025 to 02-JUL-2025.
Road work begins
.001 MILE(S) AFTER RP IS44E TO MO43 S.
Work will be done
7 days a week.
Interstate IS 44 W West
-
NEWTON COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 09-DEC-2024 to 02-JUL-2025.
Road work begins
.001 MILE(S) AFTER RP LP49N TO IS44W W.
Work will be done
7 days a week.
Interstate IS 44 W West
-
NEWTON COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 23-MAR-2025 to 02-JUL-2025.
Road work begins
.002 MILE(S) BEFORE RP IS44W TO LP49S S.
Work will be done
7 days a week.
Interstate IS 44 W West
-
NEWTON COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 30-MAR-2025 to 02-JUL-2025.
Road work begins
.013 MILE(S) BEFORE RP IS44W TO LP49S S.
Work will be done
7 days a week.
State Route MO 86 E East
-
NEWTON COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 28-MAR-2025 to 02-JUL-2025.
Road work begins
MO 43 S.
Work will be done
7 days a week.
State Route MO 86 W West
-
NEWTON COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 28-MAR-2025 to 02-JUL-2025.
Road work begins
.002 MILE(S) BEFORE MO 43 N.
Work will be done
7 days a week.
US US 60 E East
-
NEWTON COUNTY
- Expect Delays
SHOULDER WORK
Scheduled from 17-MAR-2025 to 05-JUN-2025.
Road work begins
.348 MILE(S) BEFORE CRD HAMMER RD S.
Work will be done
on weekdays only.
US US 60 E East
-
NEWTON COUNTY
- Expect Delays
SHOULDER WORK
Scheduled from 21-APR-2025 to 01-JUL-2025.
Road work begins
RT HH E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
09:00 AM
and
07:00 PM.
US US 60 E East
-
NEWTON COUNTY
- Expect Delays
SHOULDER WORK
Scheduled from 17-MAR-2025 to 01-JUN-2025.
Road work begins
.299 MILE(S) BEFORE RT Y S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
07:00 PM.
US US 60 W West
-
NEWTON COUNTY
- Expect Delays
SHOULDER WORK
Scheduled from 21-APR-2025 to 01-JUL-2025.
Road work begins
.078 MILE(S) BEFORE RT HH E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
09:00 AM
and
07:00 PM.
US US 60 W West
-
NEWTON COUNTY
- Expect Delays
SHOULDER WORK
Scheduled from 17-MAR-2025 to 01-JUN-2025.
Road work begins
.243 MILE(S) AFTER CRD FINCH DR S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
07:00 PM.
US US 60 W West
-
NEWTON COUNTY
- Expect Delays
SHOULDER WORK
Scheduled from 17-MAR-2025 to 05-JUN-2025.
Road work begins
.319 MILE(S) BEFORE CRD HAMMER RD S.
Work will be done
on weekdays only.
State Route RT AB N North
-
POLK COUNTY
- Delays Possible
RESURFACING PAVEMENT
Scheduled from 24-APR-2025 to 26-MAY-2025.
Road work begins
CRD 222ND RD S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
07:00 PM.
State Route RT AB S South
-
POLK COUNTY
- Delays Possible
RESURFACING PAVEMENT
Scheduled from 24-APR-2025 to 26-MAY-2025.
Road work begins
MO 215 S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
07:00 PM.
State Route RT UU E East
-
POLK COUNTY
- Delays Possible
RESURFACING PAVEMENT
Scheduled from 24-APR-2025 to 26-MAY-2025.
Road work begins
CRD 510TH RD E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
07:00 PM.
State Route RT UU W West
-
POLK COUNTY
- Delays Possible
RESURFACING PAVEMENT
Scheduled from 24-APR-2025 to 26-MAY-2025.
Road work begins
RT U S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
07:00 PM.
State Route MO 13 N North
-
STONE COUNTY
- Expect Delays
RESURFACING PAVEMENT
Scheduled from 20-JAN-2025 to 19-MAY-2025.
Road work begins
.001 MILE(S) AFTER MO 248 E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
06:00 PM.
State Route MO 13 S South
-
STONE COUNTY
- Expect Delays
RESURFACING PAVEMENT
Scheduled from 20-JAN-2025 to 19-JUN-2025.
Road work begins
.028 MILE(S) AFTER PVT SHADY LN E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:00 AM
and
06:00 PM.
State Route MO 13 N North
-
STONE COUNTY
- Delays Possible
INTERSECTION IMPROVEMENTS
Scheduled from 14-MAY-2025 to 19-JUN-2025.
Road work begins
.044 MILE(S) BEFORE MO 248 E.
Work will be done
7 days a week.
Work will be conducted between the hours of
08:00 AM
and
08:00 PM.
State Route MO 13 S South
-
STONE COUNTY
- Delays Possible
INTERSECTION IMPROVEMENTS
Scheduled from 14-MAY-2025 to 19-JUN-2025.
Road work begins
.181 MILE(S) BEFORE US 160 E.
Work will be done
7 days a week.
Work will be conducted between the hours of
08:00 AM
and
08:00 PM.
US US 160 E East
-
STONE COUNTY
- Delays Possible
INTERSECTION IMPROVEMENTS
Scheduled from 14-MAY-2025 to 19-JUN-2025.
Road work begins
MO 248 E.
Work will be done
7 days a week.
Work will be conducted between the hours of
08:00 AM
and
08:00 PM.
US US 160 W West
-
STONE COUNTY
- Delays Possible
INTERSECTION IMPROVEMENTS
Scheduled from 14-MAY-2025 to 19-JUN-2025.
Road work begins
.024 MILE(S) BEFORE CRD KEYSTONE RD S.
Work will be done
7 days a week.
Work will be conducted between the hours of
08:00 AM
and
08:00 PM.
State Route MO 86 E East
-
TANEY COUNTY
- Expect Delays
Project Name -
Long Creek Bridge
BRIDGE RECONSTRUCTION
Scheduled from 12-OCT-2022 to 30-MAY-2025.
Road work begins
.164 MILE(S) AFTER CRD LEISURE LN E.
Work will be done
7 days a week.
Project Web Page -
https://www.modot.org/long-creek-bridge-project
State Route MO 86 W West
-
TANEY COUNTY
- Expect Delays
Project Name -
Long Creek Bridge
BRIDGE RECONSTRUCTION
Scheduled from 12-OCT-2022 to 30-MAY-2025.
Road work begins
.218 MILE(S) AFTER PVT BRIDGEVIEW DR S.
Work will be done
7 days a week.
Project Web Page -
https://www.modot.org/long-creek-bridge-project
State Route RT M N North
-
TANEY COUNTY
- Expect Delays
PATCHING DRIVE SURFACE
Scheduled from 05-MAY-2025 to 30-MAY-2025.
Road work begins
CRD YOCUM CREEK RD E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
05:00 PM.
State Route RT M S South
-
TANEY COUNTY
- Expect Delays
PATCHING DRIVE SURFACE
Scheduled from 05-MAY-2025 to 30-MAY-2025.
Road work begins
US 160 E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
05:00 PM.
US US 160 E East
-
TANEY COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 21-APR-2025 to 23-MAY-2025.
Road work begins
.055 MILE(S) BEFORE CST SHORTY COOPER ST S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
08:00 AM
and
03:00 PM.
US US 160 W West
-
TANEY COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 21-APR-2025 to 23-MAY-2025.
Road work begins
.313 MILE(S) BEFORE MO 76 E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
08:00 AM
and
03:00 PM.
State Route MO 248 E East
-
TANEY COUNTY
- Delays Possible
SIDEWALK/ADA IMPROVEMENTS
Scheduled from 20-JAN-2025 to 31-MAY-2025.
Road work begins
.008 MILE(S) BEFORE CST CHIEFS CT E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
06:00 PM.
State Route MO 248 W West
-
TANEY COUNTY
- Delays Possible
SIDEWALK/ADA IMPROVEMENTS
Scheduled from 20-JAN-2025 to 31-MAY-2025.
Road work begins
.003 MILE(S) BEFORE US 65 N.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
06:00 PM.
State Route MO 86 E East
-
TANEY COUNTY
- Delays Possible
BRIDGE RECONSTRUCTION
Scheduled from 29-AUG-2022 to 31-DEC-2025.
Road work begins
.175 MILE(S) AFTER CRD LEISURE LN E.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
06:00 PM.
State Route MO 86 W West
-
TANEY COUNTY
- Delays Possible
BRIDGE RECONSTRUCTION
Scheduled from 29-AUG-2022 to 31-DEC-2025.
Road work begins
.194 MILE(S) AFTER PVT BRIDGEVIEW DR S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
06:00 PM.
Interstate IS 49 S South
-
VERNON COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 18-MAY-2025 to 24-MAY-2025.
Road work begins
.771 MILE(S) AFTER RP RTD TO IS49S S.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 AM
and
07:00 PM.
Interstate IS 49 N North
-
VERNON COUNTY
- No Expected Delays
BRIDGE DECK SEALING
Scheduled from 15-MAY-2025 to 22-MAY-2025.
Road work begins
.568 MILE(S) AFTER RP HIGHLAND AVE TO IS49N N.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:30 AM
and
05:30 AM.
Interstate IS 49 S South
-
VERNON COUNTY
- No Expected Delays
BRIDGE DECK SEALING
Scheduled from 19-MAY-2025 to 22-MAY-2025.
Road work begins
1.705 MILE(S) BEFORE RP IS49S TO CRD EARP RD W.
Work will be done
on weekdays only.
Work will be conducted between the hours of
06:30 AM
and
05:30 PM.
Interstate IS 44 E East
-
WEBSTER COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 04-MAY-2025 to 06-JUN-2025.
Road work begins
1.275 MILE(S) BEFORE RP IS44E TO SAMPSON RD E.
Work will be done
on weekdays and Sundays.
Work will be conducted between the hours of
07:00 PM
and
07:00 AM.
Interstate IS 44 W West
-
WEBSTER COUNTY
- Expect Delays
BRIDGE MAINTENANCE
Scheduled from 04-MAY-2025 to 06-JUN-2025.
Road work begins
.897 MILE(S) AFTER RA IS44W CONWAY W.
Work will be done
on weekdays and Sundays.
Work will be conducted between the hours of
07:00 PM
and
07:00 AM.
Interstate IS 44 W West
-
WEBSTER COUNTY
- Expect Delays
PAVEMENT REPAIR
Scheduled from 18-MAY-2025 to 31-MAY-2025.
Road work begins
.197 MILE(S) AFTER RP RTB TO IS44W W.
Work will be done
on weekdays only.
Work will be conducted between the hours of
07:00 PM
and
07:00 AM.
State Route RT A N North
-
WEBSTER COUNTY
- Expect Delays
INTERSECTION IMPROVEMENTS
Scheduled from 07-APR-2025 to 30-SEP-2025.
Road work begins
US 60 E.
Work will be done
7 days a week.
State Route RT A S South
-
WEBSTER COUNTY
- Expect Delays
INTERSECTION IMPROVEMENTS
Scheduled from 07-APR-2025 to 30-SEP-2025.
Road work begins
.243 MILE(S) BEFORE CRD NORMANDY RD E.
Work will be done
7 days a week.
US US 60 E East
-
WEBSTER COUNTY
- Delays Possible
INTERSECTION IMPROVEMENTS
Scheduled from 07-APR-2025 to 31-DEC-2025.
Road work begins
.032 MILE(S) AFTER PVT HONOR CAMP LN S.
Work will be done
7 days a week.
US US 60 W West
-
WEBSTER COUNTY
- Delays Possible
INTERSECTION IMPROVEMENTS
Scheduled from 07-APR-2025 to 31-DEC-2025.
Road work begins
.096 MILE(S) BEFORE CRD WHITE ROSE LN S.
Work will be done
7 days a week.